STEP PROGRESSES WELL

05.11.2006 [11:55]
The Sangachal Terminal Expansion Program (STEP) - ACG Phase 3 is the next important phase of construction at STEP, according to BP-Azerbaijan. The main construction works are progressing well and ...

ACG PROJECT PROGRESSING ON SCHEDULE

01.11.2006 [14:02]
Since the beginning of this year the Azeri-Chirag-Gunashli Project has progressed on schedule, BP Azerbaijan said.
The Project currently employs 10,000 people of whom 80% are Azerbaijan nationals ...

BP AZERBAIJAN AND PARTNERS TRANSPORTING AVERAGE OF 60,000 BARRELS OF OIL VIA AZERBAIJANI AND GEORGIAN RAILWAYS

01.11.2006 [13:43]
Press service of BP Azerbaijan said the company and its partners are currently transporting an average of 60,000 barrels of oil per day via the railway systems of Azerbaijan and ...

OVER 172 MLN BARRELS OF OIL TRANSPORTED VIA NREP SINCE 1997, BP AZERBAIJAN

01.11.2006 [11:41]
Press service of BP Azerbaijan said since the beginning of transportation activities in 1997 to the end of September 2006 over 172 million barrels of oil had been transported via ...

CHIRAG CURRENTLY HAS 20 WELLS

31.10.2006 [19:34]
Chirag currently has 20 wells: 14 oil producers and 6 water injectors, Bp said. Since the beginning of this year, the platform has produced over 40 million barrels (5.4 million ...

OIL PRODUCTION TO REACH 800 THOUSAND BARRELS PER DAY

31.10.2006 [13:32]
Central Azeri (CA) is currently producing from 11 wells. The platform’s operates with the 91% efficiency.
By the end of September, 2006 production from CA had been about 60 million ...

2.1 BILLION CUBIC METERS OF ASSOCIATED GAS TO BE DELIVERED BY END OF 2006

31.10.2006 [12:21]
Part of the associated gas produced from the CA, WA and now EA platforms continues to be transported via the 28” gas subsea pipeline into the Sangachal Terminal and onward ...

SANGACHAL TERMINAL IS READY TO RECEIVE FIRST GAS FROM OFFSHORE FIELD

31.10.2006 [12:20]
The onshore processing facilities, including the South Caucasus Pipeline (SCP) compressor station at the Sangachal terminal were pre-commissioned during August and September using SOCAR’s gas from ACG production. These facilities ...

ACG SPENDS $168 MILLION IN OPERATING EXPENDITURE

31.10.2006 [12:20]
During the first three quarters of 2006 Azeri-Chirag-Guneshli project spent $168 million of the planned $227 million operating expenditure and $1,849 million of the planned $2,552 million capital expenditure for ...

SHAHDENIZ GAS PROJECT 100% COMPLETE

29.10.2006 [17:43]
BP Azerbaijan said the Shahdeniz gas and condensate development project is currently 100% complete overall with onshore and offshore facilities undergoing final testing and commissioning in preparation for delivering first ...

BTC SPENT $834 MILLION DURING FIRST THREE QUARTERS OF 2006

29.10.2006 [16:36]
During the first three quarters of the year Baku-Tbilisi-Ceyhan oil pipeline spent $834 million (including the costs of line-fill and financing) in capital expenditure, press service of the BP Azerbaijan ...

DEEPWATER GUNASHLI DUQ TOPSIDES FABRICATION 66% COMPLETE

29.10.2006 [16:07]
BP Azerbaijan said the Deepwater Gunashli (Azeri-Chirag-Gunashli Phase 3) Drilling, Utilities and Quarters Platform topsides in-country fabrication progress is 66% complete.
The living quarters and drilling facilities, which are the ...

ABOUT 334 MILLION BARRELS OF OIL TRANSPORTED VIA WREP

29.10.2006 [16:07]
BP Azerbaijan said by the end of September it had transported about 334 million barrels of oil via the Western Route Export Pipeline for the AIOC (Azerbaijan International Operating Company) ...

BP PLANS TO PRODUCE 458,000 BARRELS OF OIL PER DAY AVERAGE FROM CHIRAG, CA AND WA PLATFORMS THIS YEAR

29.10.2006 [15:29]
BP Azerbaijan’s current forecast for 2006 is that it would deliver 458,000 barrels per day average for the full year, with 141,000 barrels of oil per day average produced from ...

GEORGIAN SECTION OF SCP FILLED WITH GAS

29.10.2006 [15:12]
BP Azerbaijan said following the introduction of commissioning gas into the Azerbaijani section of South Caucasus Pipeline in late May, it filled the Georgian section with gas in September.
This ...

ABOUT 11,830 AZERBAIJANIS WORKING FOR FOREIGN OIL COMPANIES IN THE COUNTRY

29.10.2006 [13:52]
The number of Azerbaijanis working for foreign oil companies in the country is about 11,830, press service of the BP Azerbaijan said.
...

ACG PROJECT PROGRESSING ON SCHEDULE

29.10.2006 [12:00]
Since the beginning of this year, the focus on safety at all Azeri-Chiraq-Gunashli Project construction sites has continued and the project has progressed on schedule, press service of the BP ...

DRILLING PROGRAM CONTINUING AT CENTRAL AZERI PLATFORM

29.10.2006 [11:23]
BP Azerbaijan said it completed the second platform-drilled well (which was a producer) at the end of July and is currently drilling the third well, which will reach total depth ...

OVER 702 THOUSAND TONS OF CRUDE SOLD AT NOVOROSSIYSK TERMINALS

26.10.2006 [12:40]
Baku-Novorossiysk pipeline has transported 3,468,634 tons of crude over the past 9 months, State Oil Company of Azerbaijan Republic said. Of this volume, 976,909 tons belong to the SOCAR 2,491,725 ...